Jutte Excavating will be mobilizing on April 27th, 2023 and beginning sheet pile installation on May 1st. Construction is projected to take three and a half weeks, with crews working for 10 hours Monday through Wednesday. Construction observation will be performed by Lawson-Fisher.
Including construction, engineering testing, and final approval, this project is targeted to be finished in six weeks. Please check back soon for a more detailed construction schedule and updates as the project progresses.
More information is available on the Harkless Drive Dike project page.